Main tasks

  • Reduction of energy costs for bitumen preparation

  • Production automation

Decision

Asphalt-concrete mixing plant No.2, stanitsa Starominskaya. Calculation of energy consumption on the basis of the results of measurement of thermal fields of the company’s tankage was done. conversion from the combustion heating system (via the flame tube wall) to the electric system with the use of leakproof tubular heating elements in the cut-in element was carried out. Automation of the bitumen heating systems was done.

Results

  • Recommendations on reduction of energy costs

  • Automation of the bitumen facility